Project MOSES, Plan of Work
The following milestones are foreseen under MOSES:
- Bed load transport for particular marine climate as determined by the ultrasonic instrument:
Quantification of the sediment transported near the bed as determined by using the ultrasonic technique. - Validation of both the used techniques, ultrasonic and marked sands: Quantification and characterization of the sedimentary transport along and cross shore in the studied head-land-bay system.
- Management GIS tool: Prevision of beaches equilibrium according to the sedimentary balance and wave conditions
The Project will be developed along 24 months according the follow overall plan:
1 - First 2 months: equipment acquisition and research grants;
2 - Field campaigns: 4 months;
3- Laboratory analysis and image processing: 5 months;
4 - Data integration and GIS tool: 4 months.