SAVE WHALES, Plan of Work


The overall work plan of the project has been divided into Work Packages (WPs), which reflect the amount and the structure of works to be undertaken. Each WP has been divided into comprehensible tasks and corresponding milestones.

  • WP1 is related to the development of one acoustic station (buoy) and its preliminary testing before installation.
  • WP2 is related to the deployment of one acoustic station (buoy) and its field testing required before operation in the framework of the full system
  • WP3 is related to the deployment of a warning system specifically developed for the proposed system.
  • WP4 is related to the development, deployment and operation of the full system, which will be undertaken in an iterative way, consisting of two phases of operation and two phases of maintenance and results assessment.
  • WP5 is related to the fieldwork validation of the fully deployed system in operation, which will be undertaken in two phases of operation (two field seasons).

The foreseen WPs and tasks of the project are been presented, while at the end a Gantt chart presenting the time-plan has been added.